Tailings Transport System – Cerro Verde Mine
General Information
Client | SMCV / Fluor |
Location | Arequipa, Peru |
Date | 2014 - 2016 |
Scope
- Installation of 60 KM of steel and HDPE pipes for tailings water, tailings dam water recovery and seepage system, installation of cyclones, pumping systems, barges.
- Massive and localized earthworks, concrete and metallic structure, mechanical assembly and piping, guides, anchor blocks.
- Electrical, mechanical, instrumentation and control installations.
Project data
11K m3
of concrete
22K m3
of excavations located
133K m3
of embankments
39K m3
of filler.
695K m3
of excavations