![](https://grupojjc.com.pe/wp-content/uploads/2022/09/JJC-Proyecto-Central-Hidroelectrica-Laja-35-MW-principal-1.jpg-1-1920x1200.jpg)
![](https://grupojjc.com.pe/wp-content/uploads/2022/09/JJC-Proyecto-Central-Hidroelectrica-Laja-35-MW-mobile.jpg-1024x1662.jpg)
Laja Hydroelectric Power Plant (35 MW)
General Information
Client | Engie – AMG Energía |
Location | Region Bio Bio, Chile |
Date | 2009 – 2012 |
Scope
- Civil works, electromechanical assembly, design and construction of the river diversion system, pumping system, earthworks, grouting, anchoring and micropiles, sheet piling.
- Supply and placement of reinforced concrete, metal inserts, slope protection, assembly of radial and flat gates, cranes, generators and turbines.
- Electrical installations.
Project data
3t
of assembly
7t
of steel
91K m3
of concrete