Rehabilitation and Improvement of the Ayacucho – Abancay Road – Section 5

General Information

Client MTC/PROVIAS NACIONAL
Location Ayacucho – Abancay
Date 2010 – 2011

Scope

  • Cold and hot asphalt pavement, flexible pavement, granular base and sub-base, earthwork.
  • Two-layer surface treatment.

Project data

19t
of steel
45K m3
of concrete
45km
of longitude
20m
of Chumbao bridge